高温工学試験研究炉の出力上昇試験; 試験経過及び結果の概要

Rise-to-power test in High Temperature Engineering Test Reactor; Test progress and summary of test results up to 30MW of reactor thermal power

中川 繁昭  ; 藤本 望; 島川 聡司; 野尻 直喜 ; 竹田 武司 ; 七種 明雄 ; 植田 祥平   ; 小嶋 崇夫; 高田 英治*; 齋藤 賢司 ; 橘 幸男 ; 足利谷 好信; 川崎 幸三; 中澤 利雄; 沢 和弘; 伊与久 達夫

Nakagawa, Shigeaki; Fujimoto, Nozomu; Shimakawa, Satoshi; Nojiri, Naoki; Takeda, Takeshi; Saikusa, Akio; Ueta, Shohei; Kojima, Takao; Takada, Eiji*; Saito, Kenji; Tachibana, Yukio; Ashikagaya, Yoshinobu; Kawasaki, Kozo; Nakazawa, Toshio; Sawa, Kazuhiro; Iyoku, Tatsuo

高温工学試験研究炉(High Temperature engineering Test Reactor : HTTR)の出力上昇試験は、30MW運転時に原子炉出口冷却材温度が850$$^{circ}C$$となる「定格運転」モードでの試験として、平成12年4月23日から原子炉出力10MWまでの出力上昇試験(1)を行い、その後、原子炉出力20MWまでの出力上昇試験(2),30MW運転時に原子炉出口冷却材温度が950$$^{circ}C$$となる「高温試験運転」モードにおいて原子炉出力20MWまでの出力上昇試験(3)を行った。定格出力30MW運転達成のための試験として平成13年10月23日から出力上昇試験(4)を開始し、平成13年12月7日に定格出力30MWの到達及び原子炉出口冷却材温度850$$^{circ}C$$の達成を確認した。出力上昇試験(4)については、平成14年3月6日まで実施し、定格出力30MWからの商用電源喪失試験をもって全ての試験検査を終了して使用前検査合格証を取得した。「定格運転」モードにおける原子炉出力30MWまでの試験結果から、原子炉、冷却系統施設等の性能を確認することができ、原子炉を安定に運転できることを確認した。また、試験で明らかとなった課題を適切に処置することで、原子炉出力30MW,原子炉出口冷却材温度950$$^{circ}C$$の達成の見通しを得た。

Rise-to-power test in the HTTR has been performed from April 23rd to June 6th in 2000 as phase 1 test up to 10MW, from January 29th to March 1st in 2001 as phase 2 test up to 20MW in the rated operation mode and from April 14th to June 8th in 2001 as phase 3 test up to 20MW in the high temperature test operation mode. Phase 4 test to achieve the thermal reactor power of 30MW started from October 23rd in 2001. On December 7th it was confirmed that the thermal reactor power reached to 30MW and the reactor outlet coolant temperature reached to 850$$^{circ}$$C. JAERI obtained the certificate of pre-operation test from MEXT because all the pre-operation tests by MEXT were passed successfully. From the test results of rise-up-power test up to 30MW, the performance of reactor and cooling system were confirmed, and it was confirmed that an operation of reactor facility could be performed safely. Some problems to be solved were found through tests. By means of solving them, the reactor operation with the reactor outlet coolant temperature of 950$$^{circ}$$C will be achievable.