Annual report on experimental operations and maintenances of mock-up model test facility with a full-scale reaction tube for HTTR hydrogen production system in 2002 fiscal year (Contract research)
Hayashi, Koji; Ohashi, Hirofumi
; Inaba, Yoshitomo
; Kato, Michio; Aita, Hideki; Morisaki, Norihiro; Takeda, Tetsuaki; Nishihara, Tetsuo
; Takada, Shoji; Inagaki, Yoshiyuki
This report describes 2002 fiscal-year experimental test operations of the mock-up test facility with a full-scale reaction tube for the HTTR hydrogen production system. The improvement works were performed in May 2002. The second experimental test operation was performed from June 2002 and the performances of the improved parts were confirmed. Periodic inspections on boiler equipment and high-pressure gas production facilities were performed from end of July 2002. The third experimental test operation was performed, from October 2002, for (a)start-up and shutdown test, (b)process change test, (c)chemical reaction shutdown test and (d)characteristics test on steam reformer. It was confirmed that the changes of helium gas temperature, caused at steam reformer, could be mitigated into the target range by the steam generator. Maintenance works of high-pressure gas production facilities were also performed in February 2003. This report is summarized with the outline and the results of the test, maintenance works and inspections, and operation records in mentioned above.