JAEA Reports

Fuel unloading work in decommissioning of the prototype fast breeder reactor Monju; First stage of Monju decommissioning project

Shiota, Yuki; Kudo, Junki; Tsuno, Hiromi; Takeuchi, Ryotaro; Ariyoshi, Hideo; Shiohama, Yasutaka; Hamano, Tomoharu; Takagi, Tsuyohiko; Nagaoki, Yoshihiro

JAEA-Technology 2023-002, 87 Pages, 2023/06

JAEA-Technology-2023-002.pdf:8.53MB

In the first stage of Monju decommissioning project, fuel unload work began to be carried out. There are two tasks in this work. One is Fuel Treatment and Storage work that gets rid of sodium on the fuel assemblies unloaded from Ex-Vessel fuel Storage Tank (EVST) and carries it in the storage pool, and the other is Fuel Unloading that the fuel assemblies in the reactor core is replaced with dummy fuels and stored in EVST. Fuel Treatment and Storage work and Fuel Unloading work are performed alternately, and 370 fuel assemblies in the core and 160 fuel assemblies in EVST are all carried to the storage pool. Monju had a large amount of sodium in the reactor vessel and EVST, and there was a residual risk of fuel failure due to the superposition of a large scale sodium fire. Therefore, in the first stage of the Monju decommissioning project, it was decided to take about 5.5 years to remove the residual risk by storing all the fuel rods in the fuel storage pool. There are few Fuel handling system of Sodium Fast Reactor in the world, so the driving record and experience are not enough. So, events that occur even if taken measure are assumed. The following three events apply to this; first, events that are difficult to prevent, events. Second, that are due to lack of experience, and final, events optimization of system is not enough. Plans were taken to suppress these events. This report summarizes the "Monju decommissioning project" work conducted so far in all four campaigns.

JAEA Reports

Fuel unloading operations -2020- in the decommissioning of the prototype fast breeder reactor "Monju"

Shiota, Yuki; Ariyoshi, Hideo; Shiohama, Yasutaka; Isobe, Yuta; Takeuchi, Ryotaro; Kudo, Junki; Hanaki, Shotaro; Hamano, Tomoharu; Takagi, Tsuyohiko

JAEA-Technology 2022-019, 95 Pages, 2022/09

JAEA-Technology-2022-019.pdf:7.59MB

In the first stage of "Monju" decommissioning project, "Fuel Unloading Operations" have been carrying out. The operations consists of two processes. The first process is "Fuel Treatment and Storage" is that the fuel assemblies unloaded from the Ex-Vessel fuel Storage Tank (EVST) are canned after sodium cleaning, and then transferred to the storage pool. The second process is "Fuel Unloading" that the fuel assemblies in the reactor core are replaced with dummy fuel assemblies and stored in the EVST. "Fuel Treatment and Storage" and "Fuel Unloading" are performed alternately until 370 fuel assemblies in the core and 160 fuel assemblies in the EVST are all transferred to the storage pool. This is a summary of "Fuel Unloading" in the third quarter of "Fuel Unloading Operation". In fiscal 2020, as "Fuel Unloading", 72 fuel assemblies and 74 blanket fuel assemblies were unloaded from the core, and stored in the EVST. From the EVST, 145 dummy fuel assemblies and 1 fixed absorber were loaded in the core instead. During these operations, a total of 36 cases alarming or equipment malfunctions classified into 4 types occurred. However, these events were estimated in advance, there were no significant events that menaces to safety of fuel assemblies and equipment. Therefore, there were no serious problem like fall of fuel assemblies and events that may affect schedule of the project like stick of gripper of ex-vessel fuel transfer machine. When equipment's work or performance fail, the operation continued with safety by elimination of causes of problem. Fuel handling system of Monju has function that is endemic to sodium cooling fast breeding reactor. Because continuous operations of fuel handling system with actual fuel assemblies start recently, we don't have as much experience as PWR and BWR. With estimation of various troubles, reduction of frequency of trouble occurrence and minimization of impacts on schedule performed.

JAEA Reports

Fuel Unloading Operations -2019- in the decommissioning of prototype fast breeder reactor "Monju"

Yabe, Takanori; Murakami, Makio; Shiota, Yuki; Isobe, Yuta; Shiohama, Yasutaka; Hamano, Tomoharu; Takagi, Tsuyohiko; Nagaoki, Yoshihiro

JAEA-Technology 2022-002, 66 Pages, 2022/07

JAEA-Technology-2022-002.pdf:10.45MB

In the first stage of "Monju" decommissioning project, "Fuel Unloading Operations" have been carrying out. The operations consists of two processes. The first process is "Fuel Treatment and Storage" is that the fuel assemblies unloaded from the Ex-Vessel fuel Storage Tank are canned after sodium cleaning, and then transferred to the storage pool. The second process is "Fuel Unloading" that the fuel assemblies in the reactor core are replaced with dummy fuel assemblies and stored in the Ex-Vessel fuel Storage Tank. "Fuel Treatment and Storage" and "Fuel Unloading" are performed alternately until 370 fuel assemblies in the core and 160 fuel assemblies in the Ex-Vessel fuel Storage Tank are all transferred to the storage pool. In fiscal 2018, as "Fuel Treatment and Storage", 86 fuel assemblies were transferred to the storage pool. As "Fuel Unloading", 76 dummy fuel assemblies were stored in the Ex-Vessel fuel Storage Tank. In fiscal 2019, as "Fuel Unloading", 60 fuel assemblies and 40 blanket fuel assemblies were unloaded from the core. These assemblies were stored in the Ex-Vessel fuel Storage Tank, and dummy fuel assemblies were loaded into the core instead. During these operations, a total of 38 cases of alarming or equipment malfunctions classified into 24 types occurred. However, no significant events that menaces to safety have occurred. The operations were continued safely by removing the direct factors for the malfunctions in the equipment operation and performance.

JAEA Reports

Fuel unloading work in decommissioning of the prototype fast breeder reactor Monju; Fuel treatment and storage work in 2018 and 2019

Shiota, Yuki; Yabe, Takanori; Murakami, Makio; Isobe, Yuta; Sato, Masami; Hamano, Tomoharu; Takagi, Tsuyohiko; Nagaoki, Yoshihiro

JAEA-Technology 2022-001, 117 Pages, 2022/07

JAEA-Technology-2022-001.pdf:25.55MB

In the first stage of Monju decommissioning project, fuel unload work began to be carried out. There are two tasks in this work. One is fuel treatment and storage work that gets rid of sodium on the fuel assemblies unloaded from Ex-Vessel fuel Storage Tank (EVST) and carries it in the storage pool, and the other is fuel unloading that the fuel assemblies in the reactor core is replaced with dummy fuels and stored in EVST. Fuel treatment and storage work and fuel unloading work are performed alternately, and 370 bodies in the core and 160 pieces in EVST are all carried to the storage pool. 86 fuel assemblies was carried to the storage pool in fuel treatment and storage work in 2018 and 76 dummy fuels were stored in EVST for fuel unloading work. During the work, 86 types and 232 alarms / malfunctions occurred, but there was no impact on safety. There was one equipment's failure at gripper's claw open / close clutch of ex-vessel fuel transfer machine B, but it was repaired and restarted. Also it was eliminated the cause of problem or concession that the equipment failure due to the sticking of the sodium compound and continuous use of the equipment. Some problems related to system control occurred, but the work was done after checking the safety. With estimation of various troubles, reduction of frequency of trouble occurrence and minimization of impacts on schedule performed.

Journal Articles

Prototype fast breeder reactor "Monju" start of unloading operation of the fuel assembly from the core

Koga, Kazuhiro*; Suzuki, Kazunori*; Takagi, Tsuyohiko; Hamano, Tomoharu

FAPIG, (196), p.8 - 15, 2020/01

The prototype fast breeder reactor Monju has already started (from June 2017) the unloading operation period (about 5.5 years: until the end of 2022) of the fuel assembly, which is the first stage of decommission. Among them, the first "Processing of fuel assembly" operation (86 in total) was conducted from August 2018 to January 2019 as the first handling of the fuel assembly. Fuji Electric provided technical support, such as dispatching technicians throughout the period, in cooperation with Japan Atomic Energy Agency for the "Processing of fuel assembly" operation, and contributed to the completion of the operation while experiencing various troubles. This manuscript introduces the contents of the first "Processing of fuel assembly" operation and the overview of the trouble status. This manuscript is a sequel to FAPIG No.194 "Prototype Fast Breeder Reactor Monju Decommissioning and Unloading Operation of the Fuel Assembly from the Core", please refer to it.

Journal Articles

Prototype fast breeder reactor "Monju" decommissioning and unloading operation of the fuel assembly from the core

Koga, Kazuhiro*; Suzuki, Kazunori*; Hamano, Tomoharu; Takagi, Tsuyohiko

FAPIG, (194), p.6 - 11, 2018/02

The prototype fast breeder reactor "Monju" was decided to decommission by Japanese government on 21 December 2016. After that, Japan Atomic Energy Agency (JAEA) submitted "Monju decommissioning basic plan" to MEXT (Charge ministry) on 13 June 2017, then the unloading operation period (about 5.5 years) of the fuel assembly, which is the first stage of decommission, has started. Fuji Electric is proceeding with various preparations in cooperation with JAEA for the safe work of the unloading operation. This manuscript introduces the outline of preparation situation such as maintenance and inspection for the unloading operation.

JAEA Reports

The Investigation related to the study on the method to withdraw the in-vessel transfer machine; Observation of the structure in the reactor vessel of the fast breeder reactor Monju

Harigae, Hitoshi; Takagi, Tsuyohiko; Hamano, Tomoharu; Nakamura, Shoichi; Oba, Toshio; Ebashi, Masaaki; Okuda, Eiichi; Kinoshita, Tomonobu

JAEA-Technology 2013-014, 150 Pages, 2013/07

JAEA-Technology-2013-014.pdf:24.38MB

In-Vessel Transfer Machine (IVTM) came off from the gripper claw in the Auxiliary Handling Machine (AHM) and fell at a height of approximately two meters during a withdrawal work of the IVTM in the Fast Breeder Reactor (FBR) Monju. The withdrawal work of IVTM from the reactor vessel by AHM was performed. The work, however, was suspended due to the excessive load alarm. To grasp the situation of the IVTM fall, observation of the machine was necessary. An interior observation and an exterior observation of the dropped IVTM were performed. As a result of these observations, the radially deformed lower end of the upper guide tube was observed at the connection part, and it was jammed in the fuel throat sleeve when the dropped IVTM was withdrawn. Based on this information, the IVTM could be safely withdrawn from the reactor vessel with the fuel throat sleeve.

Oral presentation

Purpose and plan of the fuel unloading work in fast reactor Monju

Hamano, Tomoharu

no journal, , 

no abstracts in English

Oral presentation

Study on reflection of operating experience of Prototype Fast Breeder Reactor Monju fuel handling system to the next generation FBR

Rekimoto, Masafumi; Ando, Masato; Chikazawa, Yoshitaka; Kato, Atsushi; Hamano, Tomoharu; Shiohama, Yasutaka; Miyagawa, Takayuki*; Uzawa, Masayuki*; Hara, Hiroyuki*; Yamauchi, Kanau*; et al.

no journal, , 

no abstracts in English

Oral presentation

Study on reflection of knowledge obtained from the decommissioning of the prototype fast breeder reactor "MONJU" to the fuel handling system of the next generation FBR

Rekimoto, Masafumi; Hamano, Tomoharu; Shiohama, Yasutaka; Ando, Masato*; Miyagawa, Takayuki*; Hara, Hiroyuki*; Yamauchi, Kanau*; Eda, Yuhei*; Koga, Kazuhiro*; Tanabe, Kenichi*

no journal, , 

no abstracts in English

Oral presentation

Equipment integrity conformation of fast breeder prototype reactor MONJU, 5; EVST system sodium leak countermeasure work conformation test

Kawakami, Shodai; Morimoto, Kazuyuki; Hamano, Tomoharu; Oba, Toshio

no journal, , 

no abstracts in English

11 (Records 1-11 displayed on this page)