Nakayama, Masashi; Ishii, Eiichi; Aoyagi, Kazuhei; Hayano, Akira; Murakami, Hiroaki; Ono, Hirokazu; Takeda, Masaki; Fukatsu, Yuta; Mochizuki, Akihito; Ozaki, Yusuke; et al.
JAEA-Review 2025-042, 136 Pages, 2025/12
The Horonobe Underground Research Laboratory (URL) Project is being pursued by the Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant technologies for geological disposal of high-level radioactive waste through investigating the deep geological environment within the host sedimentary rocks at Horonobe-cho in Hokkaido, north Japan. In the fiscal year 2024, we continued R&D on "Study on near-field system performance in geological environment", "Demonstration of repository design options", and "Understanding of buffering behaviour of sedimentary rock to natural perturbations". These are identified as key R&D on challenges to be tackled in the Horonobe underground research plan for the fiscal year 2020 onwards. Specifically, "full-scale engineered barrier system (EBS) performance experiment" and "solute transport experiment with model testing" were carried out as part of "Study on nearfield system performance in geological environment". "Demonstration of engineering feasibility of repository technology" and "evaluation of EBS behaviour over 100
C" were addressed for "Demonstration of repository design options". The validation of a method for assessing permeability using the Ductility Index and a method for estimating the state of in-situ ground pressure from hydraulic perturbation tests were investigated as part of the study "Understanding of buffering behaviour of sedimentary rock to natural perturbations". In FY2024, we continued construction of the East Access Shaft and the Ventilation Shaft, and construction of these shafts were completed to a depth of 500 m. After the completion of the East Access Shaft, excavation of the West Access Shaft and 500 m gallery has began. As of the end of FY2024, excavation progress is as follows, the East Access Shaft and the Ventilation Shaft were 500 m depth, the West Access Shaft was 472 m depth, 500 m gallery was 112.9 m, respectively. In the Horonobe International Project (HIP), Management Board and Joint Task Meeting was held at the Horonobe URL in June 2024 to review the progress of construction of galleries and preparations of experiments. Task Meetings to review the implementation plan for in-situ testing and analysis were also held. HIP will be implemented in two phases: Phase 1 (from FY2022 to FY2024) and Phase 2 (from FY2025 to FY2028), the research results of Phase 1 were compiled in FY2024.
Nakayama, Masashi; Ishii, Eiichi; Hayano, Akira; Aoyagi, Kazuhei; Murakami, Hiroaki; Ono, Hirokazu; Takeda, Masaki; Mochizuki, Akihito; Ozaki, Yusuke; Kimura, Shun; et al.
JAEA-Review 2025-027, 80 Pages, 2025/09
The Horonobe Underground Research Laboratory Project is being pursued by the Japan Atomic Energy Agency to enhance the reliability of relevant technologies for geological disposal of high-level radioactive waste through investigating the deep geological environment within the host sedimentary rocks at Horonobe Town in Hokkaido, north Japan. In the fiscal year 2025, we continue R&D on "Study on near-field system performance in geological environment" and "Demonstration of repository design options". These are identified as key R&D challenges to be tackled in the Horonobe underground research plan for the fiscal year 2020 onwards. In the "Study on near-field system performance in geological environment", we continue to obtain data from the full-scale engineered barrier system performance experiment, and work on the specifics of the full-scale engineered barrier system dismantling experiment. As for "Demonstration of repository design options", the investigation, design, and evaluation techniques are to be systemized at various scales, from the tunnel to the pit, by means of an organized set of evaluation methodologies for confinement performance at these respective scales. Preliminary borehole investigations will be conducted within a 500 m gallery, with the objectives of obtaining rock strength and rock permeability data, as well as surveying the extent of the excavation damaged zone surrounding the test tunnel via tomographic analysis. A planning study for the in-situ construction test will be conducted to investigate the construction of backfill material and watertight plugs. The volume of water inflow associated with the excavation of the 500 m gallery will be observed, and its magnitude will be compared with the range of water inflow predicted in the analysis. The test plan to determine the extent of the excavation damaged zone around the pit, which is planned to be constructed in the 500 m gallery, will be studied to determine the in-situ excavation damaged zone. In addition, the investigation and evaluation methods for the amount of water inflow from fractures and the extent of the excavation damaged zone around the pit will be organized. Concerning the construction and maintenance of the subsurface facilities, excavation of the West Access Shaft and the 500 m gallery will continue. It is anticipated that the construction of the facilities will be completed by the end of the fiscal year 2025. In addition, we continue R&D on the following three tasks in the Horonobe International Project; Task A: Solute transport experiment with model testing, Task B: Systematic integration of repository technology options, and Task C: Full-scale engineered barrier system dismantling experiment.
Nakayama, Masashi
JAEA-Review 2024-033, 64 Pages, 2024/09
The Horonobe Underground Research Laboratory Project is being pursued by the Japan Atomic Energy Agency to enhance the reliability of relevant technologies for geological disposal of high-level radioactive waste through investigating the deep geological environment within the host sedimentary rocks at Horonobe Town in Hokkaido, north Japan. In the fiscal year 2024, we continue R&D on "Study on near-field system performance in geological environment", "Demonstration of repository design options", and "Understanding of buffering behaviour of sedimentary rocks to natural perturbations". These are identified as key R&D challenges to be tackled in the Horonobe underground research plan for the fiscal year 2020 onwards. In the "Study on near-field system performance in geological environment", we continue to obtain data from the full-scale engineered barrier system performance experiment, and work on the specifics of the full-scale engineered barrier system dismantling experiment. We summarise the solute transport experiments for the excavation damaged zone and the effects of organic matter, micro-organisms and colloids, and develop the assessment methodology. We summarise the evaluation methodology using the deep Wakkanai Formation as a case study for block-scale solute transport experiments. As for "Demonstration of repository design options", we summarise the results of investigations and experiments on changes in the geological environment after tunnel excavation and closure, and summarise the applicability and technical challenges of the closure technology for boreholes excavated from tunnels. The systematic integration of technologies towards EBS emplacement, including the organisation of investigation and evaluation methods and analysis, will be promoted. Experiments to confirm the performance of the engineered barrier system under critical conditions, such as high temperatures (
100
C), continue the in-situ tests started in 2023.
Hata, Koji*; Niunoya, Sumio*; Uyama, Masao*; Nakaoka, Kenichi*; Fukaya, Masaaki*; Aoyagi, Kazuhei; Sakurai, Akitaka; Tanai, Kenji
JAEA-Research 2020-010, 142 Pages, 2020/11
In the geological disposal study of high-level radioactive waste, it is suggested that the excavation damaged zone (EDZ) which is created around a tunnel by the excavation will be possible to be one of the critical path of radionuclides. Especially, the progress of cracks in and around the EDZ with time affects the safety assessment of geological disposal and it is important to understand the hydraulic change due to the progress of cracks in and around EDZ. In this collaborative research, monitoring tools made by Obayashi Corporation were installed at a total of 9 locations in the three boreholes near the depth of 370 m of East Shaft at the Horonobe Underground Research Laboratory constructed in the Neogene sedimentary rock. The monitoring tool consists of one set of "optical AE sensor" for measuring of the mechanical rock mass behavior and "optical pore water pressure sensor and optical temperature sensor" for measuring of groundwater behavior. This tool was made for the purpose of selecting and analyzing of AE signal waveforms due to rock fracture during and after excavation of the target deep shaft. As a result of analyzing various measurement data including AE signal waveforms, it is able to understand the information on short-term or long-term progress of cracks in and around EDZ during and after excavation in the deep shaft. In the future, it will be possible to carry out a study that contributes to the long-term stability evaluation of EDZ in sedimentary rocks in the deep part of the Horonobe Underground Research Laboratory by evaluation based on these analytical data.
Sugiura, Yuki; Suyama, Tadahiro*; Tachi, Yukio
JAEA-Data/Code 2019-022, 40 Pages, 2020/03
Sorption behavior of radionuclides (RNs) in buffer materials, rocks and cementitious materials is one of the key processes in a safe geological disposal. This report focuses on updating of JAEA sorption database (JAEA-SDB) as a basis of integrated approach for the performance assessment (PA)-related distribution coefficient (K
) setting and development of mechanistic sorption models. K
data and their quality assurance (QA) results were updated by focusing on the following systems as potential needs extracted from our recent activities on the K
setting and development of mechanistic models, i.e., clay minerals, sedimentary rocks and cementitious materials. As a result, 6,702 K
data from 60 references were added and the total number of K
values in JAEA-SDB reached 69,679. The QA/classified K
data reached about 72% for all K
data in JAEA-SDB.
Nakayama, Masashi
JAEA-Technology 2018-006, 43 Pages, 2018/08
The Horonobe URL Project has being pursued by JAEA to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formation at Horonobe, Hokkaido. The URL Project proceeds in 3 overlapping phases, "Phase I: Surface-based investigations", "Phase II: Investigations during tunnel excavation" and "Phase III: Investigations in the underground facilities", over a period of around 20 years. The OP corrosion test was prepared from 2013 FY at Niche No.3, and heating by electric heater in simulated overpack started in November, 2014. The objective of the test is acquiring data concerned with corrosion of carbon steel OP. These data will be used in order to confirm the performance of engineered barrier system. In the OP corrosion test, the diameter of simulated OP and buffer material are 100 mm and 300 mm, respectively. Concrete support using low alkaline cement was used in order to investigate the effect of cementitious materials to OP corrosion behavior. We will measure corrosion potential of carbon steel, natural potential, pH in buffer material for several years. In this report, we describe how to make simulated OP and buffer material blocks, and set sensors, and so on.
Nakayama, Masashi; Ono, Hirokazu; Tanai, Kenji; Sugita, Yutaka; Fujita, Tomoo
JAEA-Research 2016-002, 280 Pages, 2016/06
The Horonobe Underground Research Laboratory (URL) Project has being pursued by Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formation at Horonobe, northern Hokkaido. The URL Project consists of two major research areas, "Geoscientific Research" and "Research and Development on Geological Disposal Technologies", and proceeds in three overlapping phases, "Phase I: Surface-based investigations", "Phase II: Investigations during tunnel excavation" and "Phase III: Investigations in the underground facilities", over a period of around 20 years. Phase III investigation was started in 2010 fiscal year. The in-situ experiment for performance confirmation of engineered barrier system (EBS experiment) had been prepared from 2013 to 2014 fiscal year at G.L.-350m gallery (Niche No.4), and heating by electric heater in simulated overpack had started in January, 2015. One of objectives of the experiment is acquiring data concerned with Thermal-Hydrological-Mechanical-Chemical (THMC) coupled behavior. These data will be used in order to confirm the performance of engineered barrier system. In EBS experiment, the backfill material using mixture of bentonite and muck from Horonobe URL construction was used for backfilling a part of Niche No.4. This report shows the results of properties of the backfill material, confirmation test of compaction method and making backfill material block, and so on. From these results, it was confirmed that the backfill material would satisfy target value of the permeability and the swelling pressure.
Motoshima, Takayuki*; Fujita, Tomoo; Aoyagi, Kazuhei; Shirase, Mitsuyasu*; Nago, Makito*
Proceedings of 7th International Symposium on In-situ Rock Stress (RS 2016) (Internet), 9 Pages, 2016/05
Nakayama, Masashi; Ono, Hirokazu; Nakayama, Mariko*; Kobayashi, Masato*
JAEA-Data/Code 2015-013, 53 Pages, 2015/09
The Horonobe Underground Research Laboratory (URL) Project has being pursued by Japan Atomic Energy Agency (JAEA) to enhance the reliability of relevant disposal technologies through investigations of the deep geological environment within the host sedimentary formation at Horonobe, northern Hokkaido. The URL Project consists of two major research areas, "Geoscientific Research" and "Research and Development on Geological Disposal Technologies", and proceeds in three overlapping phases, "Phase I: Surface-based investigations", "Phase II: Investigations during tunnel excavation" and "Phase III: Investigations in the underground facilities", over a period of around 20 years. Phase III investigation was started in 2010 fiscal year. The in-situ experiment for performance confirmation of engineered barrier system (EBS experiment) had been prepared from 2013 to 2014 fiscal year at G.L.-350m gallery, and heating by electric heater in simulated overpack had started in January, 2015. One of objectives of the experiment is acquiring data concerned with Thermal-Hydrological-Mechanical-Chemical (THMC) coupled behavior. These data will be used in order to confirm the performance of engineered barrier system. This report summarizes the measurement data acquired from the EBS experiment. The period of data acquisition is from December, 2014 to March, 2015. It will be periodically published summarized data of EBS experiment.
Hanamuro, Takahiro
JAEA-Review 2014-039, 69 Pages, 2014/10
The Horonobe Underground Research Laboratory Project is planned to extend over a period 20 years. The investigations will be conducted in three phases, namely "Phase 1: Surface-based investigations", "Phase 2: Construction Phase" (investigations during construction of the underground facilities) and "Phase 3: Operation phase" (research in the underground facilities). This report summarizes the results of the investigations for the 2013 fiscal year (2013/2014). The investigations, which are composed of "Geoscientific research" and "R&D on geological disposal technology", were carried out according to "Horonobe Underground Research Laboratory Project Investigation Program for the 2013 fiscal year". The results of these investigations, along with the results which were obtained in other departments of Japan Atomic Energy Agency (JAEA), are properly offered to the implementations and the safety regulations. For the sake of this, JAEA has proceeded with the project in collaboration with experts from domestic and overseas research organisations.
Tsusaka, Kimikazu*; Inagaki, Daisuke*; Niunoya, Sumio*; Jo, Mayumi*
Proceedings of 8th Asian Rock Mechanics Symposium (ARMS-8) (USB Flash Drive), 9 Pages, 2014/10
Nakayama, Masashi; Ono, Hirokazu; Shirase, Mitsuyasu*; Niunoya, Sumio*
no journal, ,
Japan Atomic Energy Agency is conducting the in-situ experiment for verification of performance of engineered barrier system in Horonobe Underground Research Laboratory. The purpose of this paper is reporting the current status of the experiment. This paper also reports the results of saturation status of buffer material blocks.